Only need preliminary notice if not in direct contract with original contractor and disciplinary action if not done
(sub of sub)
Timeframe to send Preliminary Notice:
Private and Public Work
Within 20 days of furnishing
Timeframe to record Lien/Bond claim:
Private Work
Original Contractors must file lien within earlier of 90 days of project completion or 60 days of Notice of Completion or Cessation. Other contractors/suppliers must file within earlier of 90 days of project completion or 30 days of Notice of Completion or Cessation. Notice of Mechanics Lien must be served to owner prior to filing lien claim.